The customer, GETEC Group, required a large roof structure for a VIP area at the Red Bull Ring.
The key requirement was a 15.6 m clear span, providing an open and unobstructed space underneath the roof. At the same time, the arched design had to create an attractive appearance suitable for a premium hospitality environment.
An important part of the project was also the finish – the entire structure had to be supplied in a distinctive gold colour.
MILOS team
The MILOS team evaluated the required dimensions and geometry and developed a way to adapt the existing MR1 roof system to the specific requirements of the project.
The goal was to use proven MILOS components wherever possible while developing a special solution for the unique roof geometry.
What were the challenges?
15.6 m arched span – Creating such a wide arch required a connection solution that could accommodate the specific roof geometry while maintaining the structural concept of the MR1 system. Rather than developing a completely new roof system, the challenge was to adapt the existing modular solution to achieve the required dimensions and shape.
Ballast requirements – The large roof structure also required a suitable ballast solution to provide the necessary stability. Due to the project requirements and on-site conditions, concrete ballast blocks had to be incorporated into the final design.